Ben Franklin Bridge

PATCO Schedule Change Goes Into Effect as Bridge Work Continues

New PATCO schedules for some days begin this weekend to accommodate a $103 million track rehabilitation project on the Jersey-to-Philly transit line's tracks that run along the Ben Franklin Bridge.

According to PATCO, the new schedule, which went into effect Saturday, returns PATCO service to a full, normal schedule between Monday and Thursday morning. It requires a revised schedule between mid-day Thursday and Sunday night that will stay in place through the end of October.

The track work will eventually be suspended between late October and early December before restarting and continuing again until the end of the year. Updated copies of PATCO’s schedule are available at RidePATCO.org.
 